published Friday, January 30th, 2009

Chattanooga: City eyes more waterfront fixes

Audio clip

Vance Travis

More problems have surfaced on Chattanooga’s downtown waterfront even as a $1.2 million fix to the Passage is scheduled to start in February, city officials said Thursday.

Divers are expected to be hired to find out why settlement, cracking and separating have occurred in the concrete along the Tennessee River near the Passage.

“There are other issues,” said Steve Leach, the city’s public works administrator, at a meeting of the Chattanooga Downtown Redevelopment Corp. “That’s a warning shot across the bow.”

Repairs to the Passage, the popular gathering spot near the Tennessee Aquarium, will begin next month and take until about July 1, officials said.

WHAT’S NEXT

Mike McMahan, the city’s interim attorney, said if a lawsuit is to be filed concerning the Passage repairs, it must be done by April. He said the City Council and the mayor likely will make the decision.

P&C Construction Inc. was the low bidder for the project, said Vance Travis of TWH Architects.

He said the Passage repairs coupled with other expenses related to the project could push the total price tag to between $1.5 million to $2 million. That figure would not include the cost for the divers or any needed repair work to concrete areas they might identify.

The Passage was closed last year over safety concerns, which included loose tiles and electrical grounding issues. The city had approved an $85,000 study to look at the problems of the Passage, which opened more than three years ago.

The Passage was part of then-Mayor Bob Corker’s 21st Century Waterfront Project, a $120 million public-private initiative.

The other nearby parts of the waterfront project under evaluation include the hard edge along the Tennessee River, sidewalks and steps. Caulking to fix problems with some concrete joints hasn’t fully worked, said Lee Norris, the city’s deputy administrator of public works.

After the heavy rains recently, problems remain, he said.

Mr. Norris said there are plans to hire the diving firm “pretty fast” to go into the river and inspect what may be causing the issues.

He said there is a suspicion that river currents may be creating the problems.

Mr. Leach added there may need to be handrails and guardrails put in some parts of concrete area for safety.

about Mike Pare...

Mike Pare, the deputy Business editor at the Chattanooga Times Free Press, has worked at the paper for 27 years. In addition to editing, Mike also writes Business stories and covers Volkswagen, economic development and manufacturing in Chattanooga and the surrounding area. In the past he also has covered higher education. Mike, a native of Fort Lauderdale, Fla., received a bachelor’s degree in communications from Florida Atlantic University. he worked at the Rome News-Tribune before ...

Comments do not represent the opinions of the Chattanooga Times Free Press, nor does it review every comment. Profanities, slurs and libelous remarks are prohibited. For more information you can view our Terms & Conditions and/or Ethics policy.
please login to post a comment

videos »         

photos »         

e-edition »

advertisement
advertisement
400 East 11th St., Chattanooga, TN 37403
General Information (423) 756-6900
Copyright, Permissions, Terms & Conditions, Privacy Policy, Ethics policy - Copyright ©2014, Chattanooga Publishing Company, Inc. All rights reserved.
This document may not be reprinted without the express written permission of Chattanooga Publishing Company, Inc.