SITE MAP  |  MOBILE  |  EMAILS  |  SUBSCRIBE  |  ARCHIVES  |  CONTACT US  |  ADVERTISE  |  PROMOTIONS  |  SUBMIT EVENTS  |  FEEDBACK  |  PLACE AN AD  |  RSS FEEDS
Home » News » Local/Regional News Salvaging Bellefonte
Sunday, March 29, 2009

Salvaging Bellefonte

Included in this article:      2 Comments     Audio      Video
TimesFreePress Audio
Jack Bailey

HOLLYWOOD, Ala. — When TVA canceled plans to finish its Bellefonte Nuclear Plant here in 2006, contractors began ripping out steel tubes and pipes from heat exchangers, steam generators and main condensers to sell for scrap metal.

The salvage effort proved to be short-lived.

Critics also claim it was shortsighted and could leave ratepayers short-changed.

TVA officials say they are trying to adapt to a shifting energy landscape by twice reversing their approach to America’s costliest unfinished power plant. After investing $4.2 billion in the Bellefonte plan, TVA has mothballed, canceled and then revived its construction plans over the past decade.

“The world has changed,” TVA Vice President Jack Bailey said. “The cost of new baseload generation more than doubled in price in the past three years ... so we decided to take another look at whether we should finish Bellefonte.”

TVA has taken numerous such looks over a 35-year history of starts and stops at Bellefonte.

Staff Photo by Patrick Smith
TVA Bellefonte site manager Jim Chardos, left, talks with TVA vice president Jack Bailey inside the control room at the Hollywood, Ala., nuclear site. TVA is now considering completing the site, with hopes of it being fully operational around 2020.

The federal utility halted construction of Bellefonte in the 1980s when the growth in power demand slowed and the cost of building nuclear plants rose. TVA maintained Bellefonte in an idled status for nearly two decades before finally deciding in 2006 it was too expensive and risky to finish.

TVA determined it probably could build a whole new plant for the same or less money, Mr. Bailey said.

But TVA is rethinking that approach since the projected costs have nearly doubled for the new plant design for the site — a Westinghouse Corp.-built AP-1000 reactor being developed by a consortium of utilities known as NuStart Energy LLC.

In February, TVA convinced federal regulators to reinstate the construction permit for the original Bellefonte plant even though some of the plant equipment was removed three years ago.

TVA Senior Vice President Ashok S. Bhatnagar said the reinstated construction permit from the Nuclear Regulatory Commission clears the way for TVA to begin an assessment on whether the utility should finish the original reactors at Bellefonte or build a pair of next-generation reactors at the same site. Ultimately, TVA could try to build some, or all, of four reactors at Bellefonte.

“Having this permit in place provides us a starting point for evaluating all of our options,” Mr. Bhatnagar said.

nuclear friction

PDF: NRC letter to TVA

PDF: B&W nuclear reactor

Article: TVA eyes Oak Ridge nuclear plant

PDF: Sen. Lamar Alexander speech

Article: Alexander wants 100 reactors

Article: Georgia likely site for nuke’s new design

Article: Tennessee Valley Authority urged to increase nuclear power at Bellefonte

PDF: NRC concerns about Bellefonte permit

PDF: List of proposed reactors

Article: Tennessee Valley Authority seeks green power from windy Midwest

Article: Advocates push for more green power use

PDF: TVA renewable purchases

PDF: NRC comments on Bellefonte license

Article: Salvaging Bellefonte

PDF: NRC Bellefonte report

PDF: TVA renewable power

Article: Tennessee: TVA considers more renewable power

Article:Union rips Tennessee Valley Authority guard changes

Article: Tennessee: NRC OKs new work at Bellefonte

PDF: NRC Bellefonte permits

Article: Chattanooga: Nuclear power touted as solution to U.S. energy woes

PDF: Sequoyah order

Article: Tennessee: TVA guard falsified records, report says

Article: Prepping for a nuclear rebound

Article: Lining up for nuclear revival

PDF: Draft GNEP impact study

Article: East Tennessee makes push for nuclear fuel recycling site

Article: Tennessee Valley Authority power cheaper, more reliable, but operating costs still above average

Article:Tennessee: Area aglow over nuclear growth

Article: Chattanooga: Capitol ambitions held for cell Wamp says fuel unit tested at UTC lands $3.5 million in taxpayer money

Article: Lawmakers say lower gas prices shouldn’t dampen focus on energy

Article: Tennessee Valley Authority urges conservation to limit rate impact

Article: Tennessee: Staying beneath the debt cap

Article:Tennessee Valley Authority cuts contract for nuclear security

Article: Tennessee Valley Authority rate increase electrifies Congress

Article: Tennessee Valley Authority to study reviving Bellefonte reactors

Article: New Energy Reform Act of 2008

Article: Chattanooga: Law enforcement learns about transuranic waste

Article: Chattanooga: Nuclear may power local jobs

Article: Tennessee: New nuclear plants get more expensive

Environmentalists warming up to nuclear energy options

TVA a player in nuclear’s comeback

Nuclear waste shipments in Chattanooga growing sharply

Nuclear poised to take slice of energy pie

But TVA’s shifting approach at Bellefonte has drawn fire from both supporters and opponents of nuclear power. The unprecedented reinstatement of Bellefonte’s construction permit also divided NRC commissioners last month.

Anti-nuclear activists object to TVA building any more reactors.

Louis Zeller, nuclear campaign coordinator for the Blue Ridge Environmental Defense League, said the hydrology and water are inadequate to support any reactors at Bellefonte. He vows to fight plans to either finish the original plant or build the new AP-1000 reactors at the site.

“There are serious safety questions about this site,” he said. “If you try to finish the old reactors, you just don’t know how much of that plant is usable and how much is beyond repair and is outdated. The new AP-1000 design is an unproven technology.”

Supporters of nuclear power insist Bellefonte can be a reliable source of power but question TVA’s on-and-off approach to building the plant.

Dr. Bob Doggart, a former senior engineering specialist at TVA who now serves as the managing lead assessor for the British Institute of Nondestructive Testing LLC, has long argued for TVA to finish at least the Unit 1 reactor at Bellefonte.

“We spent more than $4 billion of the ratepayers’ money on what I think is one of the best designed and built nuclear plants in America,” he said. “To allow outsiders to come in and remove key equipment for virtually nothing was unbelievably foolish.”

Dr. Doggart previously estimated that the Unit 1 reactor at Bellefonte could have been finished in a couple of years for no more than $400 million, although other TVA estimates were far higher.

But replacing the steam generators, heat condensers and other systems gutted when TVA tried to scrap the plant could add hundreds of millions of dollars to any completion cost, TVA officials concede. Mr. Bhatnagar said TVA transferred $49 million of equipment from Bellefonte to other TVA fossil and nuclear plants and sold another $16 million of stainless steel pipes and tubes to scrap vendors.

licensing debate

The revival of a canceled nuclear plant would be unprecedented in U.S. history.

The Nuclear Regulatory Commission voted 3-1 in February to reactivate the construction permit for Bellefonte that TVA gave up in 2006. But the new permit is only for a “terminated plant,” and TVA will have to re-establish some programs before the NRC permit could be upgraded to allow any actual construction to begin.

Even granting the terminated plant construction permit was opposed by NRC Commissioner Gregory Jaczko.

Bellefonte starts and stops

* 1974 — Construction permit issued and building begins

* 1985 — Construction halted on Unit 2, then 55 percent complete

* 1988 — Construction halted on Unit 1, then 88 percent complete

* 1992 — Engineering work resumed to prepare for restart of construction

* 1994 — Stone & Webster estimates finishing Bellefonte will cost $2.6 billion. Engineering work halted

* 1996 — TVA studies option of converting plant to combined-cycle, natural gas

* 1998 — Gas conversion option dropped. TVA offers plant to the Department of Energy to make bomb-grade tritium.

* 1998 — DOE picks existing TVA plants to produce tritium.

* 2001 — Texaco proposes using Bellefonte as site for coal gasification plant.

* 2001 — Chattanooga financier Franklin Haney offers to finance completion of Bellefonte as a nuclear plant.

* 2002 — Texaco drops proposal. TVA turns down Haney offer.

* 2004 — TVA enters into talks with other utilities and joins NuStart to pursue new plant design for site.

* 2005 — NuStart picks Bellefonte as site for Westinghouse AP1000 nuclear plant. TVA withdraws construction permit for original plant.

* 2006 — NuStart to prepare licensing permit and engineering design for new plant

* 2006 — TVA sells stainless steel tubing, pipes at Bellefonte for scrap metal. Other equipment transferred to other plants

* 2008 — TVA decides to consider reviving Bellefonte units 1 and 2

* 2009 — Nuclear Regulatory Commission reinstates construction for original reactors in terminated status

* 2010 — TVA to conduct engineering scoping studies and likely decide which, if any, reactors to build

* 2011 — If approved and financed, construction work on new plant could begin.

* 2018-2020 — New plant could begin power generation.

Sources: Tennessee Valley Authority, Nuclear Regulatory Commission

In his dissent, Mr. Jaczko noted that Bellefonte hasn’t been under any oversight or rules since the construction permit was withdrawn.

“To say that a withdrawal does not matter is saying that not having a permit for over two years is the same as having had a permit for those two years,” he said. “A regulatory agency should, at a minimum, defend its regulations and the need for them.”

finished look

TVA plans to spend $15 million in the current fiscal year to try to prepare for the next step at Bellefonte. If the TVA board decides to proceed, the utility could spend far more next year to do a more detailed engineering analysis of the plant, Mr. Bhatnagar said.

Even with some of the equipment removed, the Bellefonte plant appears to be largely complete from a physical standpoint. The cooling towers, office and turbine buildings and reactor containment building were all finished in the 1980s and most of the key plant components are already in place, including most of the control room equipment.

But other than the diesel generators used to produce backup power, Bellefonte has never generated any electricity. The turbine building is so old that TVA now is having to put a new roof on the facility as part of its normal maintenance.

Jim Chardos, the site manager who has worked most of the past decade at Bellefonte, said most of the plant equipment is still new and the structure is sound and well documented. Some electrical equipment remains energized to maintain its reliability.

Unlike the recovery and completion programs at Sequoyah and Watts Bar, TVA appears to have maintained better engineering records at Bellefonte.

With two thick concrete walls, Bellefonte’s reactor containment building also is as secure as any nuclear plant in the country, Mr. Bailey said.

When TVA halted construction of the Unit 2 reactor at Bellefonte in 1985, the unit was considered to be 58 percent complete. Three years later when work ceased on the Unit 1 reactor, TVA estimated that unit was 88 percent complete.

Mr. Bhatnagar now estimates the units are probably only about half complete since some of the original equipment would now have to be replaced or upgraded to meet today’s standards.

Neighbors to the 1,600-acre nuclear site said they are eager to see something come of TVA’s investment.

Goodrich “Dus” Rogers, president of the Jackson County Economic Development Authority, said the plant has been like a roller coaster of ups and downs over the past three decades.

“But I think the community overall here is supportive of nuclear power and wants the jobs that this plant would create,” he said.

Construction of Bellefonte is expected to create more than 2,000 temporary jobs and a twin-reactor plant would employ more than 1,000 full-time TVA workers.

“We want Bellefonte built, either the original plant, the new plant or both,” he said.

Play this video
Construction that cost $4 billion began on the TVA Bellefonte nuclear site in Hollywood, Ala., in 1974 but was never completed. TVA explored different options for use of the facility, even selling steel and other infrastructure items from the plant. Now TVA will have to replace some of that infrastructure in hopes of opening the facility around 2020.

2 Comments

This is a prime example of why the board should not be political appointees. There should be professioal business managers that must live with decisions made. The idiots that voted to scrap should be named and I hope are no longer in any decision making positions.

Username: lmdfw | On: March 29, 2009 at 1:17 a.m.
Did you find this comment to be useful? Yes | No
0 of 0 people found this comment useful.

Excellent article and history about Bellefonte.

I live 4.5 miles from Bellefonte. Every day I see the ghostly glow from the idle cooling towers. I do not support the use of nuclear power for the generation of electrical power at Bellefonte. Nuclear power is excessively expensive, there is the waste issue and TVA has not been honest with the public concerning the Bellefonte Project. The TVA displays an atrocious record of irresponsibility in the construction and management of the Bellefonte project.

TVA has not been truthful with the public concerning Bellefonte and the various issues involved with safety, risks and environmental factors in continuing the Bellefonte Nuclear project. The TVA refuses to disclose a means to finance the nuclear construction. They also refuse to disclose accurate construction costs.

The recent deceit involving TVA in the accurate disclosure of events and testing at the Harriman Tn. disaster and the Widows Creek Plant hazardous materials spill creates serious questions of reliability and TRUST in reporting of accidents. It has been my experiance with public relations personnel and observations of executive management the TVA has created a "culture of deceit" within the management of this Governmental Utility.

There must be no questions of reliability and trust concerning the operation of nuclear facilities. TVA fails the test. TVA has also attempted to circumvent NRC policy in licensing procedures. It has also been reported that TVA and the NRC has meet with Nuclear Contractors in secret to formulate plans for continuing the construction of Bellefonte. This action is irresponsible and circumvents nuclear licensing procedures. TVA has violated the public trust and should not be allowed to construct any further nuclear facilities. They can not afford the construction costs without extravagant and unneeded raises in electric power rates further exasperating an already serious economical crisis for citizens in the TVA service area.

The TVA investigated and formulated alternative fuels for the operation of Bellefonte in 1997. This plan recommended the use of Natural Gas. It is my belief and that of others that natural gas conversion is the safest and most economical plan for Bellefonte which meets the future electrical needs for the area without the excessive risks of nuclear waste and costs. TVA's Executive Summary for the Bellefonte Conversion: http://www.tva.gov/environment/reports/b...

Username: GarryMorgan | On: March 30, 2009 at 7:49 p.m.
Did you find this comment to be useful? Yes | No
0 of 0 people found this comment useful.

Post a comment

Commenting requires registration.

Username:
Password: (Forgotten your password?)

Comment:

Posted comments do not represent the opinions of the Chattanooga Times Free Press. Profanities, slurs and libelous remarks are prohibited. To view complete guidelines for submitting content, comments and feedback, click here.

Only In Tomorrow's TimesFreePress
Tech Talk
Shop
Search Local Items

Classifieds/Place and Ad
Search Local Items

Jobs
Enter keyword or select from below..
Homes
Search for your home...
Cars
Search for your car...
Find a Business

© Copyright, permissions and privacy policy Copyright ©2008, Chattanooga Publishing Company, Inc. All rights reserved.
This document may not be reprinted without the express written permission of Chattanooga Publishing Company, Inc.