published Wednesday, June 6th, 2012

Mile-long extension added to Cleveland-Bradley County Greenway

Follow the latest Cleveland news on Twitter

CLEVELAND, Tenn. - There's a final punch list to complete, but the major work on an extension of the Cleveland-Bradley County Greenway is done.

The Cleveland Daily Banner reported that, with paving done last week, the trail is now an uninterrupted four-mile footpath.

Construction on this latest phase of the project began last summer and was delayed by damaging flooding in September and then slowed by a rainy winter season.

The new extension is about 1.2 miles long.

The trail was begun in the 1970s.

about Associated Press...

The Associated Press

Other National Articles

videos »         

photos »         

e-edition »

advertisement
advertisement
400 East 11th St., Chattanooga, TN 37403
General Information (423) 756-6900
Copyright, Permissions, Terms & Conditions, Privacy Policy, Ethics policy - Copyright ©2014, Chattanooga Publishing Company, Inc. All rights reserved.
This document may not be reprinted without the express written permission of Chattanooga Publishing Company, Inc.