Promises of easier nuclear construction fall short

photo In this Friday, June 13, 2014 photo, Buzz Miller, executive vice president of nuclear development at Southern Co., stands in front of the high-pressure vessel that will be used in a new nuclear reactor at Plant Vogtle power plant in Waynesboro, Ga. Before it started building, the nuclear industry promised its new generation of plants would be constructed using giant Lego-like modules that make building faster, cheaper and produce a higher-quality result. Instead, the Louisiana factory building these modules has failed to master quality control rules, stick to schedule or replicate the approved designs, adding time and significant cost to first-of-their-kind projects.

WAYNESBORO, Ga. - The U.S. nuclear industry has started building its first new plants in decades using prefabricated Lego-like blocks meant to save time and money and revive the once-promising energy source.

So far, it's not working.

Quality and cost problems have cropped up again, raising questions about whether nuclear power ever will be able to compete with other electricity sources. The first two reactors built after a 16-year lull, Southern Co.'s Vogtle plant in Georgia and SCANA Corp.'s VC Summer plant in South Carolina, are being assembled in large modules. Large chunks of the modules are built off-site, in an effort to improve quality and avoid the chronic cost overruns that all but killed the nuclear industry when the first wave of plants was being built in the 1960s and 1970s.

Analysts say engineers created designs that were hard or impossible to make, according to interviews and regulatory filings reviewed by The Associated Press. The factory in Louisiana that constructed the prefabricated sections struggled to meet strict quality rules. Utility companies got early warnings but proved unable to avoid the problems. Now the firms leading the project are phasing out the Louisiana factory for work on the biggest modules and contracting with new manufacturers.

Few power companies are building brand-new nuclear plants right now because gas-fired plants are so cheap by comparison. But if construction costs can be controlled, the nuclear industry might have a long-term chance. Future gas prices are always uncertain, and stricter U.S. pollution rules could make nuclear plants more attractive since they produce no greenhouse gasses. The difficulties producing modules are one factor that caused schedules to slide. The first of the two new reactors at each site in Georgia and South Carolina were supposed to be operating in 2016, but that timetable has now been pushed into 2017 or early 2018. In Georgia, Southern Co. expects to spend $646 million more than the originally budgeted $6.1 billion on its share of the project.

Joseph "Buzz" Miller, a Southern Co. executive tasked with building the nuclear plant in Georgia, thinks building in modules can still work, despite the recent trouble. "Has it for the first units resulted in a lot of time savings? No," he said. "But does it have promise? Yes."

The utilities in Georgia and South Carolina purchased power plants that use the AP1000 reactor designed by Westinghouse Electric Co. Its modules can weigh hundreds of tons and dwarf buildings.

The Shaw Modular Solutions factory in Lake Charles, La., was to produce large, prefabricated chunks of the plants.

"You can build these components in a closed environment," Edward Day VI, an executive vice president for Southern Co., told regulators in a 2008 hearing. "Your productivity goes way up."

The large sections are shipped to Plant Vogtle in eastern Georgia and the Summer generation station in South Carolina, where workers inspect them, weld them into large modules, then hoist them into place with massive derricks.

A nuclear engineer working for Georgia's utility regulators, William Jacobs Jr., warned in December 2010 that the Louisiana factory had experienced delays due to quality assurance, design and fabrication problems. He called it a "significant concern."

Inspectors for the U.S. Nuclear Regulatory Commission halted their first review of the plant the following month, saying it was not ready for in-depth scrutiny. Follow-up inspections found more issues with the plant's quality assurance programs. NRC officials proposed a $36,400 fine against The Shaw Group for firing a quality insurance supervisor elsewhere in its company who warned a potentially faulty part may have been shipped to a project in New Mexico. The fine was dropped after the company agreed to changes. The agency also said workers at the Lake Charles facility feared raising safety and quality concerns to their supervisors.

The NRC concluded that a welder at the factory took a qualification test for another worker in 2010, and that a supervisor knew but did not report it.

"I think the Lake Charles facility is just on a learning curve that they can't seem to get on top of," said Anthony James, who monitors the South Carolina nuclear project for the South Carolina Office of Regulatory Staff, which oversees utilities.

Chicago Bridge & Iron Co. N.V. acquired The Shaw Group in February 2013. The new owners replaced top managers at the factory, adopted a less antagonistic stance toward inspectors and allowed Southern Co. and SCANA Corp. to conduct more oversight. CBI spokeswoman Gentry Brann refused interview requests.

The factory is now sending partially completed modules directly to the construction site to be inspected and repaired under the careful watch of the utility companies.

Going forward, Westinghouse and CB&I are phasing out the Lake Charles factory and hiring firms in Oregon, Florida and Virginia to build the largest modules, Southern Co. spokesman Brian Green said. The Lake Charles factory will still produce smaller pieces such as piping, valves or instrumentation.

Upcoming Events