Section of Mountain Creek Road to close for 4 months

Road closed tile
Road closed tile

The City of Chattanooga Public Works Department (PWD) will soon be stabilizing a failing section of Mountain Creek Road.

Stabilization requires the construction of a retaining wall along the western edge of pavement located between 5007 Mountain Creek Road and 5117 Mountain Creek Road. The construction zone will involve approximately 500 linear feet and encompass the entire width of the roadway for mobilization of personnel, heavy equipment, material storage, and excavation.

Public Works will mobilize its forces and close the road beginning Jan. 22, 2018. Currently, it is scheduled to reopen by May 21, 2018 but completion is subject to delay due to inclement weather or unforeseen circumstances. We will contact you with any significant changes to the anticipated schedule.


Detours will be posted directing access to properties north of the construction zone via HWY 27 to Mountain Creek Road, and access to properties south of the construction zone via HWY 27 to Morrison Springs Road. For public safety, all vehicle, pedestrian, and bicycle traffic will be prohibited during the closure within the construction zone.

In order to view a map of these closures, please visit: http://www.chattanooga.gov/transportation/traffic-engineering-a-operations/special-events-a-street-closures.

Upcoming Events