South Carolina utility votes to stop building two billion-dollar nuclear reactors

FILE - This April 9, 2012 file photo shows construction well underway for two new nuclear reactors at the V.C. Summer Nuclear Station in Jenkinsville, S.C. South Carolina's state-owned public utility has voted to stop construction on two billion-dollar nuclear reactors. The reactors were set to be among the first new nuclear reactors built in the U.S. in decades, but the vote by Santee Cooper’s board on Monday, July 31, 2017 likely ends their future. (AP Photo/Jeffrey Collins)
FILE - This April 9, 2012 file photo shows construction well underway for two new nuclear reactors at the V.C. Summer Nuclear Station in Jenkinsville, S.C. South Carolina's state-owned public utility has voted to stop construction on two billion-dollar nuclear reactors. The reactors were set to be among the first new nuclear reactors built in the U.S. in decades, but the vote by Santee Cooper’s board on Monday, July 31, 2017 likely ends their future. (AP Photo/Jeffrey Collins)

COLUMBIA, S.C. - South Carolina's state-owned utility voted Monday to stop building two billion-dollar nuclear reactors, likely ending the project that has been beset by delays and cost overruns.

The reactors were set to be among the first new nuclear reactors built in the U.S. in decades.

Santee Cooper's board said the decision to end construction will save customers an estimated $7 billion. The utility had already spent $5 billion, and completing the project would have cost an additional $8 billion and $3.4 billion in interest. It also likely wouldn't be finished until 2024. The first reactor was supposed to be online in August 2019.

Santee Cooper owns 45 percent of the project. South Carolina Electric & Gas owns 55 percent. Santee Cooper chief executive Lonnie Carter said he expected SCE&G to make a similar announcement soon.

Next-generation nukes

The Westinghouse AP 1000 nuclear plant design was certified by the Nuclear Regulatory Commission in December 2005. Southern utilities that have planned for new design include:› Tennessee Valley Authority was selected in 2005 to be the first plant to test the AP1000 design at TVA’s Bellefonte Nuclear Plant in Hollywood, Ala., but those plans were scrapped in 2009 after cost estimates rose and power demand growth slowed.› Georgia Power Co. contracted in 2008 with Westinghouse Corp. for the two AP1000 reactors at its Plant Vogtle near Waynesboro, Ga., which is also partially owned by Dalton Utilities. The new units have taken longer and cost more than originally forecast, and last week Southern Nuclear took over management of the project from Westinghouse, which filed for bankruptcy in March and paid Southern $3.7 billion.› Santee Cooper voted Monday to suspend work on two AP1000 reactors at the V.C. Summer plant near Columbia, S.C., due to cost overruns. Westinghouse will pay $2.2 billion to South Carolina Electric & Gas and Santee Cooper for its failure to complete the project within budget.

"It became obvious to us" to end construction, Carter said.

The project has been shrouded in doubt since earlier this year, when primary contractor Westinghouse filed for bankruptcy protection.

The utilities announced last week that Westinghouse's parent company, Toshiba Corp., agreed to jointly pay them $2.2 billion regardless of whether the reactors are ever completed.

The reactors were planned for the V.C. Summer Nuclear Station north of Columbia. Construction began with state approval in 2009, and the project was so far about one-third completed.

Environmental groups have called on state regulators to order SCE&G to abandon the projects. They also want customers to be refunded at least some of the billions they'd paid upfront through rates that have increased yearly since 2009.

A 2007 state law allows electric utilities to collect money from customers to finance a project before it generates power. Construction now accounts for 18 percent of the electric bills of SCE&G's residential customers.

Santee Cooper has increased rates five times to pay for the escalating costs. But the Public Service Commission has no authority over the state-owned utility.

The commission has set a hearing on the environmental group's request for October.

Whether the commission can order the utility to refund customers and how much are matters of debate. That could require proof the utility gave regulators faulty information.

Last month, Toshiba agreed to pay $3.7 billion toward two nuclear reactors in Georgia that also were being built by Westinghouse. Georgia Power Co. officials said last week they plan to finish the new Vogtle reactors, which are projected to cost more than $14 billion.

"We remain focused on safety and quality as we complete this transition (from Westinghouse to Southern Nuclear)," said Mark Rauckhorst, executive vice president for the Vogtle 3 and 4 project.

Upcoming Events