Velsicol Chemical wants to complete environmental cleanup of its Alton Park site by covering the 30- to 40-acre parcel with an 18-inch layer of clean soil that officials say will cap any remaining contamination and eliminate any health risk.
The company operated on the site for 44 years, producing chemicals used in herbicides as well as food preservatives, until it closed in 2007.
Gary Hermann, Velsicol Chemical’s senior environmental projects manager, said most contaminants on the site were removed between 1999 and 2001.
“We’ve already removed many millions of pounds of contaminated soil from the site, so what the remedy is, is to basically put on a soil barrier,” Hermann said. “The soil barrier will keep the soil where it’s at. What little contamination that’s left will stay where it’s at.”
But former Velsicol employee Dwight Jones said capping and covering the site won’t be enough to protect people from chemicals that leaked into the ground over four decades.
