TIMELINE FOR NEW NUKES• 2010: Site preparation began for two new reactors – Units 3 and 4 – at Plant Vogtle near Waynesboro, Ga.• Late 2011: The Nuclear Regulatory Commission is expected to certify the design of the Westinghouse AP1000 and grant a combined operating license for the new reactors to be built.• 2016: Unit 3 reactor at Plant Vogtle to be completed.• 2017: Unit 4 reactor at Plant Vogtle to be completedSource: Southern Nuclear Operating Co.
By the end of the year, Georgia Power, Dalton Utilities and the other owners of the Plant Vogtle nuclear plant hope to secure the first combined operating license to build and operate two new reactors near Waynesboro, Ga.
But in a news conference Monday, anti-nuclear groups charged that the containment building in the new reactor design is still not secure enough to avoid the risk of a deadly radioactive leak. And they said the Nuclear Regulatory Commission, which has recommended approval of the design, is ignoring those issues.
Arnold Gundersen, a former nuclear industry executive hired by a dozen anti-nuclear groups, said the proposed Westinghouse reactor design — known as the AP1000 — is more susceptible than today’s reactors to cracks and holes which have shown up in at least 40 currently operating plants.
“A large body of work indicates that radiation releases from containment failures in the AP1000 could exceed federal safety limits by up to 1,000-fold,” Gundersen, the chief engineer at Fairewinds Associates, an engineering consultant, told reporters during the media briefing.