Bellefonte costs rise again: TVA rejects offer from private company to finish Alabama plant

bellefonte-costs-rise-again
bellefonte-costs-rise-again

OXFORD, Miss. – The Tennessee Valley Authority may never need the power from America’s biggest unfinished power plant. But if TVA decides to finish its stalled Bellefonte Nuclear Plant in Alabama, it will likely cost nearly twice as much as earlier estimates and won’t be financed by former Chattanooga billionaire Franklin L. Haney.

TVA President Bill Johnson told TVA directors Thursday a new assessment projects that finishing just one of the two reactors would cost $7.4 billion to $8.7 billion. The earlier estimate was $4.9 billion.

The numbers and the recent decline in TVA power sales mean there’s no need to finish Bellefonte anytime soon. Johnson said a proposal from former TVA Chairman Dennis Bottorff and Haney to help the utility finance the work doesn’t add up and won’t be done in time to qualify for needed federal tax credits.

“Their proposal is not an operative proposal because we cannot justify, in the near term, completing the plant to meet the needs of our customers,” Johnson said.

Haney, who first offered a plan to help finance Bellefonte’s completion more than a decade ago, has spent much of this year lobbying Congress, TVA distributors and industrial customers.