The Tennessee Valley Authority board of directors acted Tuesday on its power to approve a major electricity use request and delegated authority to the CEO to apply for nuclear reactor license extensions.
TVA plans to invest $13 billion in one of the largest capital spending campaigns in its 93-year history to meet rising demand from artificial intelligence data centers and manufacturing. Its board now has six of nine possible members.
The board approves electric rate increases, executive compensation and major investments in new power plants and nuclear innovation for the nation’s largest public utility.
Here is a breakdown of the unanimous votes the board took at Tuesday’s meeting in Knoxville.
Korea Zinc demand
The board approved a request from Crucible Zinc, a subsidiary of Korea Zinc, for more than 100 megawatts of power.