The Chickamauga lock replacement project is fully funded and expected to be finished in December 2028, U.S. Rep. Chuck Fleischmann, R-Ooltewah, said Monday as the U.S. Army Corps of Engineers celebrated completion of newly constructed walls on the lock’s upstream approach.
The completion of C.J. Mahan Construction Co.’s $68 million contract moves a portion of the replacement project forward despite the termination of a separate contract with Shimmick Construction earlier this year.
“It’s a proud day for the entire delivery team,” said Lt. Col. Guillermo Guandique, commander of the Corps’ Nashville District, during a ribbon-cutting ceremony Monday.
C.J. Mahan completed the upstream approach walls and holds another contract for downstream approach walls and other work needed to bring the replacement lock into operation. Shimmick was contracted to construct the replacement lock chamber before the Corps terminated its contract in May.
(READ MORE: Chickamauga lock contractor to lay off 183 workers, notice says)
The Corps has since assigned portions of Shimmick’s unfinished work to other contractors, including C.J. Mahan, according to an official statement provided Monday by Corps public affairs officer Lee Roberts.
