Plans to rehabilitate James Boulevard continue, now with the aid of Alexian Village.
The senior-care facility has committed $50,000 toward the project, said town of Signal Mountain Mayor Bill Lusk. Discussions have been ongoing about the possibility of Alexian contributing to the project because of the amount of construction traffic to and from the facility, which has further damaged the historic road.
Town Public Works Director Loretta Hopper said the total project cost is $638,800. The town is only responsible for $127,760 – 20 percent – thanks to a grant from the Tennessee Department of Transportation that comes with an 80 percent match. The town was also responsible for the costs of a trolley track study – $6,200 – and a historic survey report – $4,500 – said Hopper, both of which have been completed.
The preliminary phase of the project will hopefully come to a close soon, Hopper said. The required historic survey report has been passed back and forth between town and TDOT officials, and after a few more minor comments are made, it will be sent to the State Historic Preservation Office.
If it is approved, the town will receive a notice to proceed with the design.