TVA finishes $326 million repair of Boone Dam in Northeast Tennessee

Just ahead of the start of the summer boating season and the Memorial Day weekend, the Tennessee Valley Authority on Wednesday celebrated the completion of its biggest and most expensive repair of one of its 29 hydroelectric dams to restore full hydro generation and lake levels at the Boone Reservoir in Northeast Tennessee.

After 2 million hours of work and $326 million of dam remediation expenses, TVA crews completed the construction of a seepage barrier beneath and around the Boone Dam on the South Fork Holston River. The repairs made over the past seven years will limit water leaks at one of the three hydro units at the 70-year-old dam.

Although the repairs were the costliest ever for a TVA hydroelectric facility and forced the shutdown for more than seven years of one of the three hydroelectric generating units at the Boone Dam, the project was ultimately done within budget and on time, TVA officials said.

(READ MORE: Carbon removal technologies to get $3.5 billion federal investment)

“At the onset of this project, we made a commitment that we would complete this effort safely within seven years and we would do it right the first time with a high-quality repair,” TVA Chief Operating Officer Don Moul said in prepared remarks during a ceremony Wednesday afternoon at TVA’s Boone Dam. “Boone Lake is a local treasure, and I want to thank everyone for their patience as we completed the important dam safety work.”