Report says Bellefonte Nuclear Plant risks too great

report-says-bellefonte-risks-too-great
report-says-bellefonte-risks-too-great
photo Staff file photo: Supporters and critics of nuclear power squared off Tuesday night at a public hearing about the future of the Bellefonte Nuclear Plant.

With the clock ticking down to TVA’s board consideration next week of the $4 billion to $5 billion completion of Bellefonte Nuclear Plant, the Southern Alliance for Clean Energy unveiled a new report Tuesday alleging “seven major factors” why the project should not go forward.

Calling Bellefonte “TVA’s bad nuclear bet,” the alliance’s executive director, Stephen Smith, said the 37-year-old, half-finished and cannibalized nuclear plant has document problems that make it “too risky” for safety and fiscal reasons.

“We’re not convinced Bellefonte is salvageable,” he said, noting a potential for cracking in foundations and reactor containment areas similar to cracks discovered in recent years in a nuclear plant in Florida.

“These are [documentation] issues that TVA may have with regulators that will be extremely costly, if not insurmountable,” Smith said. “And with TVA’s debt ceiling, they [TVA] don’t have the wiggle room they did in the ’70s to throw good money after bad.”

He and Fairewinds Associates consultant Arnold Gundersen said Nuclear Regulatory Commission inspections also show water damage to the foundation of Bellefonte, caused by TVA turning off sump pumps when the plant was mothballed.