The future of one of America’s biggest unfinished construction projects will remain in limbo for at least a few more months while the Tennessee Valley Authority considers its options.
Utility officials said Tuesday they are delaying a planned April 16 board decision whether to finish the original reactor or build a new one at the Bellefonte Nuclear Plant in Hollywood, Ala.
“It’s an important decision for TVA and its customers, so we want to take the time to make sure we make a prudent decision,” TVA spokesman Terry Johnson said.
An environmental assessment released last year found that finishing the Unit 1 reactor begun in 1974 would be cheaper than building a next-generation Westinghouse AP-1000 reactor.
TVA in 2006 said it would build the new AP-1000. But as the projected cost rose above $3 billion, officials began rethinking.