Business Briefs: TVA completes refueling at Sequoyah nuclear plant

Tennessee Valley Authority headquarters and TVA logo
Tennessee Valley Authority headquarters and TVA logo

TVA completes refueling at Sequoyah nuclear plant

Just in time for this weekend’s frigid weather, the oldest reactor at the Sequoyah Nuclear Plant near Soddy-Daisy returned to full power Thursday after TVA workers refueled the reactor by replacing 72 of the unit’s 193 fuel assemblies.

The Unit 1 reactor completed a scheduled refueling and maintenance outage Wednesday. At full power, the reactor is capable of generating 1,200 megawatts, or enough power for 650,000 homes.

During the outage, detailed inspections of the reactor vessel were conducted to confirm all components continued to meet or exceed all design requirements. Other major maintenance activities included replacing or refurbishing a number of motors, valves and other plant components, as well as several modifications for improving safety.

“The entire Sequoyah team, supported by more than 900 supplemental contract workers, completed approximately 11,000 activities,” said Greg Boerschig, Sequoyah site vice president.