Work completed so far
* Removed existing electrical (completed mid-September)* Constructed new electrical infrastructure (completed mid-November)* Performed preliminary concrete repairs (completed late November)* Finalized new electrical infrastructure (completed Dec. 11)The city plans to transition from electrical to the contractor for the liner work. The major liner work begins after Christmas and continues through the end of the project in late February.Source: City of Chattanooga
Some business owners near the Wilcox Tunnel say their sales have dropped by more than half during the four months it has been closed for repairs, and they wonder if city officials care.
“They’re not thinking of businesses or residents in this area,” said John Taylor, area businessman and former Chattanooga councilman. “They’re not thinking about the pedestrians trying to get through. This simply shows the city is unconcerned for our community.”
Taylor and other merchants said they’ve seen so little work at the tunnel they anticipate that in or before February, the city will ask for an extension because its renovation will be incomplete.