Repairs to slope near East Ridge to begin Friday morning, finish by April 16

Staff file photo by C.B. Schmelter / Two workers look at the damage caused by a landslide on the east side of the Bachman Tunnels on Thursday, March 18, 2021, in East Ridge, Tenn. The Tennessee Department of Transportation said permanent repairs will start Friday at 9 a.m. and be completed by April 16.
Staff file photo by C.B. Schmelter / Two workers look at the damage caused by a landslide on the east side of the Bachman Tunnels on Thursday, March 18, 2021, in East Ridge, Tenn. The Tennessee Department of Transportation said permanent repairs will start Friday at 9 a.m. and be completed by April 16.

Crews will start making permanent repairs at 9 a.m. Friday on the slope near the East Ridge tunnels where last week’s mudslide forced the tunnels to be temporarily closed.

The area to be repaired is adjacent to the westbound tunnel – the side heading out of East Ridge toward downtown Chattanooga – which will be closed for repairs expected to be completed by April 16, according to TDOT spokesperson Jennifer Flynn.

The eastbound tunnel will remain open but drivers in the area should watch for construction vehicles, Flynn said in a statement.

“The contractor will also repair an additional slide area after they complete the first site, but the work will be done off the roadway and will not affect traffic,” she said.

Traffic normally using the westbound tunnel will be detoured to Germantown Road, according to Flynn.