The federal cost for cleaning up lead-contaminated soil on Chattanooga’s Southside has jumped more than fourfold, from $25.8 million to $113.5 million over the next decade.
The spike comes as sample testing by contractors for the Environmental Protection Agency determined at least 433,000 cubic yards of lead-contaminated soil should be removed from the area to protect residents from lead poisoning. The project entails removal and remediation work to clean up 1,892 properties.
“The number of properties requiring remediation and the cost of the remediation are significantly higher than originally estimated,” EPA said in a notice of its budget change.
The soil in eight different Southside neighborhoods were contaminated over the past century from residue generated at more than 60 iron, brass and bronze foundries that operated in Chattanooga for nearly a century, until the 1980s.
EPA spokesman Jason McDonald said foundry sand from those factories was used as fill dirt and spread as topsoil at hundreds of properties before lead in such sand was discovered and later regulated by EPA.