COLUMBIA, S.C. (AP) – A utility will brief South Carolina regulators Tuesday on its plans to end construction of two nuclear reactors that customers have already paid billions to build.
The state Public Service Commission will hear from executives with SCANA, the parent company of South Carolina Electric & Gas. Both SCE&G and state-owned Santee Cooper decided Monday to scuttle the project at V.C. Summer Nuclear Station north of Columbia. The hearing could supply answers on how that decision will affect customers.
Private utility SCE&G, which owns 55 percent of the project, must win state approval of its abandonment plans.
The project has been shrouded in doubt since Westinghouse, hired as primary contractor in 2008, filed for bankruptcy protection earlier this year.
The utilities have since determined costs to finish the project could top $20 billion. They have already jointly spent roughly $10 billion over a series of delays and cost overruns.