Audit: Tennessee must curb Eastman plant’s emissions

FILE - A portion of the Eastman Chemical Co. plant can be seen along the South Holston River in Kingsport, Tenn., on May 16, 2001. Nine years after the EPA first found Tennessee’s Eastman Chemical Company was polluting the air with unsafe levels of sulfur dioxide, the state is still working to bring down emissions. (AP Photo/Wade Payne)
FILE - A portion of the Eastman Chemical Co. plant can be seen along the South Holston River in Kingsport, Tenn., on May 16, 2001. Nine years after the EPA first found Tennessee’s Eastman Chemical Company was polluting the air with unsafe levels of sulfur dioxide, the state is still working to bring down emissions. (AP Photo/Wade Payne)

NASHVILLE, Tenn. (AP) — Nine years after the EPA first found Tennessee’s Eastman Chemical Company was polluting the air with unsafe levels of sulfur dioxide from its coal-burning power plants, the state is still working to bring the company into compliance with national air quality standards.

That’s according to a new state audit of the Tennessee Department of Environment and Conservation, released to the public this week, that also found continuing problems with the department’s data management.

The Environmental Protection Agency tightened its standards for sulfur dioxide emissions in 2010, saying the new limits were “necessary to provide protection of public health with an adequate margin of safety, especially for children, the elderly and those with asthma.”

The agency designated the area around the Eastman Chemical Company, in Kingston, out of compliance in 2013. To meet air quality standards, the Tennessee Department of Environment and Conservation worked with Eastman on a plan that included converting five of the company’s 14 coal-fired boilers to natural gas.

But in 2019, air monitoring at a nearby elementary school found sulfur dioxide levels were still too high. The department is in the process of submitting a new plan to the EPA that includes emission controls on two of Eastman’s remaining coal-burning boilers. According to TDEC documents, Eastman put in temporary controls in mid-2019 and finished installing the permanent controls late last year.