PORTLAND, Maine (AP) — A battle over a $1 billion transmission line that won all regulatory approvals only to be rebuked by state residents in a referendum now comes down to nine regular folks.
In a rare move, a jury is being asked to decide a complicated constitutional matter — whether developers have a vested right to complete the 145-mile (233-kilometer) project, which would supply Canadian hydropower to the New England power grid.
The constitutionality of the statewide referendum on the project depends on the jury’s decision on the narrow vested-rights issue. And the case could turn on a simple majority of jurors.
“We’re not aware of a similar instance in which the fate of a large energy asset rests in the hands of a jury. This is an unusual circumstance,” Timothy Fox, vice president of Clear View Partners, an energy research firm in Washington, D.C., said before the trial began Monday.
The courtroom was packed Monday.