Traffic has been turned loose on the last piece of the $32 million Interstate 24-South Broad Street improvement project on Chattanooga’s Southside as the newly constructed frontage road paralleling the freeway quietly opened this week.
The project stands at 91.66% complete and on budget, the Tennessee Department of Transportation said.
“The frontage road was fully opened to traffic Monday morning,” department spokesperson Rae Anne Bradley said Friday in an email. “The contractor will have a few minor work items to complete after that date related to cleaning up the project.”
On Friday, traffic was relatively light as motorists discovered the new road was open. A few pedestrians were using the new sidewalks, and traffic from South Broad was able to take it all the way to the I-24 on-ramp at Market Street. The frontage road — really an extended ramp — has no signage naming it.
The contractor, Charleston, Tennessee-based Wright Brothers Construction, started work in September 2020 and was dogged by supply chain issues in the summer of 2022. Still, the Tennessee Department of Transportation said crews remained on schedule for an Aug. 31 finish.