TVA considering sites in Jackson County, Alabama, for energy storage, backup power production

Staff photo by Olivia Ross / Diamond core drilling is done. Core drilling was done by TVA at one of the two potential pumped storage sites in Jackson County, Alabama on Wednesday, September 13, 2023.
Staff photo by Olivia Ross / Diamond core drilling is done. Core drilling was done by TVA at one of the two potential pumped storage sites in Jackson County, Alabama on Wednesday, September 13, 2023.

PISGAH, Alabama — The Tennessee Valley Authority is turning to the sun for much of its future power with plans over the next two decades to buy or build solar farms capable of producing 10,000 megawatts of solar power generation.

But to help balance the electricity needed when the sun doesn’t shine, TVA is also drilling underground to explore the options of a power storage system.

At two sites along the Tennessee River and Sand Mountain in Northeast Alabama, TVA is studying the feasibility of building pumped storage facilities similar to the one erected four decades ago atop and within Raccoon Mountain just west of Chattanooga.

Pumped storage facilities, which have already been built by electric utilities at 42 sites across the nation, act like a giant storage battery. By building a reservoir atop Sand Mountain, TVA could pump water from the Tennessee River for storage and then drain the water through hydroelectric turbines within the mountain to produce electricity when it is needed the most.

“This is a very mature and efficient way to store energy and it is an important way to keep the electric grid stable and reliable when other sources of power are not available,” said Scottie Barrentine, TVA’s project manager for the study. “When power demand increases or one of our units trips and goes offline, the pumped storage units can be started up and producing power in a matter of minutes to help meet any immediate need.”