Earlier this year, utility regulators approved Georgia Power’s plan to beef up its system with more fossil-fueled power assets and battery storage, mostly to serve an onslaught of energy-intensive data centers the company says are driving up electricity demand.
On Wednesday, a key part of that plan — the construction of three new oil and gas-burning units at Plant Yates in Coweta County — came under the microscope during hearings at the Georgia Public Service Commission (PSC).
The hearings come as other electricity providers in Georgia and beyond also double down on greenhouse gas-releasing fossil fuels, despite record global temperatures and other growing climate concerns.
Here’s what you need to know about the Yates expansion and what comes next.
Cost questions