A global developer with plans for a 300-acre data center in Bradley County has sued the county over stringent regulations the county placed on the computing facilities earlier this year.
SDCL, a London-based firm with U.S. headquarters in New York City, sued the county Friday, according to documents shared Monday by Bradley County Mayor Gary Davis.
In 2024, the developer purchased 306 acres behind Walker Valley High School in Charleston, part of unincorporated Bradley County, for a data center campus.
The lawsuit alleges the Bradley County Commission violated state law when its members unanimously approved zoning amendments in April that make it nearly impossible to build data centers in unincorporated parts of the county, according to an overview SDCL sent to Davis.
“Today we filed a complaint in court, asserting that the process required under Tennessee law was not followed in the county’s April 2026 vote regarding data center regulations,” Lolita Jackson, executive director of sustainable cities at SDCL, said in an email to Davis on Friday.