U.S. District Court Judge Eli Richardson on Tuesday handed a significant win to Metro in the lawsuit filed by data center developer DC Blox in August.
Richardson dismissed DC Blox’s claims. The company, which is seeking to build a data center at a site adjacent to the Nashville Zoo, had alleged that Metro’s “relentless efforts” to block the development illegally singled out the company.
The lawsuit is focused on Metro’s implementation of new zoning regulations and a moratorium on new approvals of such projects, not on the city’s pending effort to seize the property using the condemnation process.
“Plaintiff may believe, and is entitled to believe and contend, that it received a raw deal from (or was sandbagged by) the imposition of the Moratorium after it purchased the Property,” Richardson wrote in his opinion. “However, a raw deal or sandbagging — real or imagined, without more — does not a federal lawsuit make.”
The legal battle is far from over, as Richardson gave DC Blox 21 days to amend some of the dismissed claims, and other avenues of relief remain outstanding.