Days after wastewater officials said they hoped to reopen South Chickamauga Creek to recreational activities this month, a state filing related to a second sewage leak said it will be a year or longer before the creek is open again.
The second leak was 15,000 gallons, while the Oct. 6 leak was 642,000 gallons.
Still, the Oct. 16 report submitted by the city to the Tennessee Department of Environment and Conservation said work will take at least 12 months, and the creek will be closed to all recreational activities until after work is completed.
City officials said Monday at a press conference that the new closure timeline is not due to environmental concerns so much as practical considerations about how public access could impact the work.
“What we’re kind of worried about is if we have to keep our bypass pipes in place across the creek, that might be a hazard to boaters,” Wastewater Administrator Mark Heinzer said at the press conference. “That’s really the only thing that would keep it restricted, not the actual issue of environmental overflows, because that’s been stopped.”