TVA must order gas turbines seven years ahead as data centers compete

TVA / TVA is having to order gas turbines five years before delivery and seven years before operations as global backlogs grow. Utility crews are photographed installing the first of 16 GE Vernova aeroderivative generators at the Kingston gas plant under construction in Harriman, Tenn.
TVA / TVA is having to order gas turbines five years before delivery and seven years before operations as global backlogs grow. Utility crews are photographed installing the first of 16 GE Vernova aeroderivative generators at the Kingston gas plant under construction in Harriman, Tenn.


Large-scale data centers are upending business as usual for the Tennessee Valley Authority not only because of their high electricity needs, but also because they are competing with utilities for power equipment.

Some of the data centers, like Elon Musk’s xAI supercomputer in Memphis, are generating their own electricity by burning gas in the same kind of turbines TVA needs for its gas plants. That’s on top of the 300 megawatts of electricity TVA has already agreed to supply to xAI from the federal utility’s own plants, enough to power around 180,000 homes at once.

As TVA builds more than 3,600 megawatts of gas-fired power plants and plans for up to 26,000 megawatts in total new gas plants, it has had to order gas turbines two years earlier than typical. Data centers have increased the global backlog for gas turbines as they become customers for a piece of equipment, setting off a global scramble.