Tracy City, Tenn., Public Utility General Manager Tommy McFarland, on the intake structure catwalk, says the project to raise the Big Fiery Gizzard Dam by 7 feet will almost double the reservoir’s footprint. The new water level will reach almost to the large water pipe on the left and to the tree line in the distance.A couple of Tracy City, Tenn., residents say a $5.5 million project to enlarge the reservoir used by the town for drinking water is too expensive to undertake without an OK from taxpayers.
Tracy City’s charter requires approval of two-thirds of the town’s registered voters if a debt exceeds 5 percent of the taxable property assessment, according to resident Barbara J. Camm.
She said the $3.3 million loan needed for the project is four times more debt than the charter allows without a taxpayer vote. She calculates that amount at $759,756.75, using current data from the county property assessor’s office.
But Jeff Oldham, Nashville-based bond attorney for the Tracy City Water Works, said state law supersedes the City Charter, providing instead for a 20-day public protest period that he said drew no opponents before the utility got the loan.
“The General Assembly intended that the Local Government Public Obligations Act, rather than any local government charter, serve as Tracy City’s bonding authority,” Oldham states in an email. “If 10 percent of voters petition the issuance of a bond, then the bond may not be issued until the bond issue is approved by voter referendum.