The Tennessee Valley Authority has completed the refueling of its newest reactor at the Sequoyah Nuclear Power Plant near Soddy-Daisy.
Plant operators will be increasing power at the Unit 2 reactor this week until it reaches full power and generates enough electricity to serve 650,000 homes.
During the outage over the past couple of weeks, TVA replaced 80 of the unit’s 193 fuel assemblies and conducted detailed inspections of the reactor vessel to confirm all components meet design requirements to try to limit unplanned outages like the four this year on Unit 1 that resulted in extra regulatory oversight of the plant. During the Unit 2 outage, TVA also rebuilt a high pressure turbine and replaced both a reactor coolant pump motor and a main steam safety valve.
“The entire Sequoyah team, supported by more than 700 supplemental contract workers, successfully completed approximately 10,000 activities while working more than 138,000 man-hours,” said Chris Schwarz, Sequoyah’s new site vice president, said in a statement.
The refueling is the first since the U.S. Nuclear Regulatory Commission elevated its oversight of Sequoyah last month due to the excessive number of reactor trips during 2015.