Chattanooga business owners complain of slow progress on Wilcox Tunnel repair, doubt city’s February completion date

Staff Photo by Dan Henry / The Chattanooga Times Free Press- 12/16/15. Business owners Tia Taylor-Clark with Jane of Trades Upscale Resale, left, and Taylor Funeral Home director John Taylor, right, discuss how the closure of the Wilcox Tunnel has negatively affected their businesses while standing in front of the closed thoroughfare on Wednesday, December 16, 2015.
Staff Photo by Dan Henry / The Chattanooga Times Free Press- 12/16/15. Business owners Tia Taylor-Clark with Jane of Trades Upscale Resale, left, and Taylor Funeral Home director John Taylor, right, discuss how the closure of the Wilcox Tunnel has negatively affected their businesses while standing in front of the closed thoroughfare on Wednesday, December 16, 2015.

Work completed so far

* Removed existing electrical (completed mid-September)* Constructed new electrical infrastructure (completed mid-November)* Performed preliminary concrete repairs (completed late November)* Finalized new electrical infrastructure (completed Dec. 11)The city plans to transition from electrical to the contractor for the liner work. The major liner work begins after Christmas and continues through the end of the project in late February.Source: City of Chattanooga

Some business owners near the Wilcox Tunnel say their sales have dropped by more than half during the four months it has been closed for repairs, and they wonder if city officials care.

“They’re not thinking of businesses or residents in this area,” said John Taylor, area businessman and former Chattanooga councilman. “They’re not thinking about the pedestrians trying to get through. This simply shows the city is unconcerned for our community.”

Taylor and other merchants said they’ve seen so little work at the tunnel they anticipate that in or before February, the city will ask for an extension because its renovation will be incomplete.