Chattanooga City Council reviews $250 million wastewater program

Mike Marino with Jacobs Engineering gives a presentation on the city's wastewater infrastructure during an afternoon agenda session at the City Council building in Chattanooga on March 29.
Mike Marino with Jacobs Engineering gives a presentation on the city's wastewater infrastructure during an afternoon agenda session at the City Council building in Chattanooga on March 29.

The Chattanooga City Council wants to know if the city is getting what it is paying for with a comprehensive $250 million program intended to reduce – or where possible, eliminate – raw sewage overflows into the Tennessee River.

Since the city signed a 2013 agreement with the U.S. Environmental Protection Agency, Chattanooga Public Works has launched a 17-year, two-phase plan to replace and repair wastewater lines and increase the capacity of sewage facilities. A key element is preventing overflows by reducing stormwater infiltration into the sewer network through damaged pipes and manholes.

The city has borrowed $66.8 million through the Tennessee Department of Environment and Conservation and will discuss taking out another $42.5 million TDEC loan on Tuesday.

After a briefing recently by Jacobs Engineering Group, the consultants overseeing the wastewater overhaul, council members expressed concerns about the program’s accountability and end results.

“We’d like to know, with all these millions of dollars, is it going in the right direction?” council Chairwoman Carol Berz said. “When all this money is spent, when all of this happens, what does that mean?”