US nuclear plant up for sale at fraction of cost

In this Wednesday, Sept. 7, 2016 photo, sit manager, Jim Chardos, lowers his head as he talks about Tennessee Valley Authority selling the unfinished Bellefonte Nuclear Plant, in Hollywood, Ala. After spending more than 40 years and $5 billion on an unfinished nuclear power plant in northeastern Alabama, the nation's largest federal utility is preparing to sell the property at a fraction of its cost.
 (AP Photo/Brynn Anderson)
In this Wednesday, Sept. 7, 2016 photo, sit manager, Jim Chardos, lowers his head as he talks about Tennessee Valley Authority selling the unfinished Bellefonte Nuclear Plant, in Hollywood, Ala. After spending more than 40 years and $5 billion on an unfinished nuclear power plant in northeastern Alabama, the nation's largest federal utility is preparing to sell the property at a fraction of its cost. (AP Photo/Brynn Anderson)

HOLLYWOOD, Ala. (AP) – After spending more than 40 years and $5 billion on an unfinished nuclear power plant in northeastern Alabama, the nation’s largest federal utility is preparing to sell the property at a fraction of its cost.

The Tennessee Valley Authority has set a minimum bid of $36.4 million for its Bellefonte Nuclear Plant and the 1,600 surrounding acres of waterfront property on the Tennessee River. The buyer gets two unfinished nuclear reactors, transmission lines, office and warehouse buildings, eight miles of roads, a 1,000-space parking lot and more.

Initial bids are due Monday, and at least one company has publicly expressed interest in the site with plans to use it for alternative energy production. But TVA says it isn’t particular about what the purchaser does – using the site for power production, industrial manufacturing, recreation or even residences would all be fine with the agency, said spokesman Scott Fiedler.

“It’s all about jobs and investment, and that’s our primary goal for selling this property,” said Fielder. TVA hopes to close the deal in October.

The sale is bittersweet for site manager Jim Chardos, who went to work at Bellefonte in 1994 expecting it to be finished as a nuclear power plant. All these years later, he commutes 90 minutes each way to work to oversee a plant that has never been stocked with radioactive fuel or used either of its reactors to generate a single watt of electricity.