America’s oldest nuclear power plant will shut down on Sept. 17, but the Oyster Creek plant near the New Jersey shore will stay right where it is for the next 60 years.
Officials with the U.S. Nuclear Regulatory Commission held a briefing Monday on shutdown plans for Oyster Creek, which opened in 1969. They said Chicago-based Exelon plans to remove the remaining nuclear fuel rods from storage pools and put them into dry storage within 5 years of the shutdown date.
All told, it will cost $1.4 billion to shut down the plant; Exelon currently has $982.1 million of that set aside in a decommissioning account, NRC officials said.
Although the plant will stop producing electricity just before summer ends, radioactive material could be on site until the late 2070s, if not later.
“There is no national repository for spent fuel at this point,” said Neil Sheehan, a spokesman for the commission. “The only option for operators is to store the spent nuclear fuel on site.”