Hydrology report outlines causes of summer flooding in Ringgold, Ga.

CTI storm water system analysis and drainage area map of Ringgold, Georgia. / Contributed photo
CTI storm water system analysis and drainage area map of Ringgold, Georgia. / Contributed photo

To re-create eye witness accounts of a July 9, 2019, storm that flooded and shut down several businesses in downtown Ringgold, engineers had to simulate a 500-year storm event, meaning that there is a one in 500 chance of it occurring.

CTI engineer Philip Schofield said such a storm would be the equivalent of about 5 inches of rain in 15 minutes, which was consistent with eye witness accounts, but it’s more likely that there was a blockage in a nearby sewage line that pushed the water and flooded businesses on Nashville Street.

Following that summer storm, at the Ringgold City Council meeting on Aug. 12, officials voted to spend $18,430 on two consulting contracts with CTI Engineers of Chattanooga to study the drainage system around the historic downtown and central business district. The first of those contracts was for a $12,000 study examining the main drainage basin on Claiborne Street, the results of which were released at the council’s meeting on Jan. 27.