Skip to main content
Monday, November 16, 2026Nov 16

I-24 to Broad Street ramp opening delayed, but completion date, cost remain the same

Staff photo by Olivia Ross  / Construction continues at the I-24, South Broad Street interchange on Friday, September 23, 2022. With initial hopes of being complete by August,TDOT says contractor crews have been slowed by supply chain issues and materials shortages.
Staff photo by Olivia Ross / Construction continues at the I-24, South Broad Street interchange on Friday, September 23, 2022. With initial hopes of being complete by August,TDOT says contractor crews have been slowed by supply chain issues and materials shortages.

The ramp from eastbound Interstate 24 to South Broad Street on the Southside in downtown Chattanooga was set to open by August, but problems getting materials have delayed cement work.

The $32 million interchange improvement project on Friday was at 71.8% completion, Tennessee Department of Transportation spokeswoman Rae-Anne Bradley said in an email.

“Due to supply chain issues and material shortages, the concrete ramps and barrier walls took longer than expected to complete,” Bradley said.

In July, Bradley warned those problems were beginning to crop up.

The contractor, Charleston, Tennessee-based Wright Brothers Construction, still expects to complete the project by Aug. 31, 2023, and the price tag remains the same, she said. The project began in fall of 2020.