When plans were first developed for a bigger replacement lock at the Chickamauga Dam nearly two decades ago, the project was projected to cost less than $300 million and was expected to provide a quicker and better water passageway on the Tennessee River by 2020, if not sooner.
But with congressional funding delays and additional problems with supplies, labor and “concrete growth” in the existing lock chamber, the expense of one of Chattanooga’s costliest building projects has jumped more than three fold and been delayed by nearly a decade from the original projections.
In a briefing to the Inland Waterways User Board earlier this month, the Army Corps of Engineers estimates the total cost of building the replacement Chickamauga Lock has swelled to $954.4 million, up from the previous estimate of $757 million. Although the Corps previously said the project was fully funded, completing the new lock is now projected to need more money in future years from the Inland Waterways Trust Fund, which pays for all lock and dam projects in the U.S.
In a presentation to the Inland Waterways Users Board meeting on April 13 in Pittsburgh, the project manager for the new lock, Kevin Jasper, said the contractor building the replacement lock “is significantly behind” the original projected completion in November, and efforts to speed the project “have not been successful to date.”
Oakland, California-based Shimmick Construction is the prime contractor to construct the new 110-by-600-foot lock chamber on the Tennessee River below the Chickamauga Dam. The new and bigger lock will replace the smaller lock that was built when the Chickamauga Dam was first completed in 1940. The new lock will be able to handle nine times as many barges at one time to help speed river shipments in the region.