The Tennessee Valley Authority is planning $28 million of transmission upgrades in Polk County, Tennessee, and Cherokee County, North Carolina, to help improve power reliability.
TVA is proposing to erect a switching station and 27 miles of new power lines to connect with the Apalachia Dam near Murphy, North Carolina, and extend power to the southeast.
TVA spokesman Scott Fiedler said the new transmission corridor through the mountains of East Tennessee and Western North Carolina will provide a second source of power to the substation and increase the capacity of TVA’s Ranger substation for growth and further economic development in growing parts of Cherokee and Polk counties.
The new line will be built using primarily steel, H-frame structures with the potential for steel towers and single-pole structures, Fiedler said.
“We are doing the project to improve power reliability in the area,” he said in an emailed statement.