TVA activates 3 more natural gas turbines in Kentucky

TVA / Three new natural gas  combustion turbine units began power production Sunday at TVA's Paradise plant in Western Kentucky
TVA / Three new natural gas combustion turbine units began power production Sunday at TVA's Paradise plant in Western Kentucky

Three years after shutting down what was once one of TVA’s biggest coal plants in Kentucky, the Tennessee Valley Authority activated three new natural gas combustion turbine units over the weekend on the same site near Drakesboro, Kentucky, to help meet power demand during the cold winter months.

The $500 million project adds three new natural gas units to provide another 750 megawatts of generation capacity — enough to supply the electricity needs for more than 440,000 average homes. The new turbines were built at the former Paradise Fossil Plant where TVA operated coal power plants for 57 years on the Green River made famous by folk singer John Prine in his 1971 song “Paradise.”

The Paradise gas units, which began commercial operation Sunday to meet their year-end completion schedule, are designed to withstand temperature extremes and to start within minutes when electricity demand increases. During testing, the three units came online to full power within 11 minutes.

The new gas units are in addition to 1,100 megawatts of natural gas generation built at the Paradise plant in 2017 to replace the first two coal-fired units that shut down that same year.

The natural gas turbines at Paradise are capable of producing nearly 78% of the 2,379 megawatts of power TVA previously got from its three major coal units at Paradise. Although environmental groups have blasted TVA for its continued use of carbon-emitting fossil fuels, TVA said the new gas units reduce carbon emissions by more than 60% compared to the coal units they replace and are more flexible in stopping and starting generation as power demand warrants.