Ramp from Shallowford Road to I-75 to close Friday to Sunday

Staff photo by Matt Hamilton / On Oct. 16, 2025, work continues on the ramp onto Interstate 75 south at Exit 5. Here, a crew works on steel reinforcements on the new ramp to Hamilton Place Boulevard from I-75 south. The entrance ramp from Shallowford Road to I-75 south will be closed from 8 p.m. Oct. 17, 2025, to 6 a.m. Oct. 20, 2025, for the installation of bridge beams over the ramp.
Staff photo by Matt Hamilton / On Oct. 16, 2025, work continues on the ramp onto Interstate 75 south at Exit 5. Here, a crew works on steel reinforcements on the new ramp to Hamilton Place Boulevard from I-75 south. The entrance ramp from Shallowford Road to I-75 south will be closed from 8 p.m. Oct. 17, 2025, to 6 a.m. Oct. 20, 2025, for the installation of bridge beams over the ramp.

The state’s $83 million interchange project at Hamilton Place has reached 50% completion, as a weekend ramp closure is set for the Shallowford Road-Interstate 75 connection near Hamilton Place mall.

Beginning at 8 p.m. Friday, Tennessee Department of Transportation contract crews will close the existing entrance ramp from Shallowford Road to Interstate 75 south until 6 a.m. Monday for installation of steel bridge beams for the new I-75 south exit ramp to Hamilton Place Boulevard, according to the state’s transportation agency.

The full closure is required due to the size and type of beams, which require extended crane holds to complete.

“This weekend’s work is a moderate milestone that’ll allow work to continue on the new bridge parallel to I-75,” agency spokesperson Gracie Shamblin said in an email. “Most of the work right now is on the new bridges, getting ready to pour bridge decks and set beams on the new I-75 southbound off-ramp bridge. The contractor is also working at Hamilton Place Boulevard.”

The contractor hopes to move to the next phase on the Hamilton Place Boulevard portion by Thanksgiving, Shamblin said. The projected completion date for the project is May 31, 2027, and the work is on track to finish on time.