The Tennessee Valley Authority is preparing for a major increase in electricity demand across the Southeast, and data centers are at the center of it.

TVA’s 2026 integrated resource plan identifies population growth and data center development as the primary drivers of rising electricity demand across its seven-state service area. The plan looks out through 2040 and calls for as much as 26 gigawatts of new natural gas generation alone. It goes before TVA’s board Aug. 20.

At the same time, TVA is trying to change how some of the region’s largest electricity users pay for power.

In February, TVA sent a letter to the 153 local power companies that buy its electricity, proposing changes to its wholesale rate structure for data centers and other “very large, rapidly scaling loads.” The proposed changes include new pricing and capacity requirements intended to give utilities more flexibility to respond as new loads come online.

TVA is in a position to shape one of the biggest questions surrounding the data center boom: Who pays for the power needed to support it?