Dade County won’t let company study industrial park site for data center after all

A pod at a dcBLOX data center in Chattanooga holds servers from various companies Friday, Sept. 22, 2017. The facility enables customers to transfer, back up and restore large business-critical data sets and systems.
Staff file photo / A pod at a dcBLOX data center in Chattanooga holds servers from various companies Friday, Sept. 22, 2017. A proposed Dade County data center site won't be studied after the county said on Nov. 16, 2026, it would not be allowed.

A development company won’t get past square one on building a data center in Trenton, Georgia, after the Dade County Industrial Development Authority voted unanimously not to allow the company to assess the site.

At its regular meeting Monday, the authority agreed to rescind a letter of intent it signed with Masterworks Atlanta LLC, which would have allowed the company to begin to evaluate the feasibility of property in the Dade County Industrial Park.

Pulling the letter also means approximately 200 acres will not be sold to Masterworks, authority Executive Director Evan Stone said by phone.

The letter of intent, originally signed Oct. 16, would have given Masterworks permission to move forward with studying the industrial park to evaluate whether Georgia Power could provide sufficient energy to the site.

The potential data center could have had an interior footprint of approximately 40 acres, the same size of about 30 American football fields, and may have used 300 megawatts of electricity, roughly equivalent to the power used by 250,000 homes in a year.