NRC chairwoman sees ‘no show stoppers’ at Watts Bar nuclear plant

nrc-prepares-for-licensing-vote-next-year-as
nrc-prepares-for-licensing-vote-next-year-as
photo TVA Senior Vice President Mike Skaggs points to work being done at the Watts Bar Nuclear Plant as NRC Chairwoman Allison Macfarlane, right, and an unidentified TVA worker listen.

WATTS BAR AT A GLANCE• Location: 1,700 acre site on the Tennessee River near Spring City, Tenn.• History: Construction began in 1973; work suspended in 1988; and restarted in 2008; Unit 1 started in 1996• Design: Two Westinghouse pressurized water reactors• Power output: Each unit can generate 1,150 megawatts, or enough power for two cities the size of Chattanooga• Staff: 3,200 workers are employed in building the unit 2 reactor• Status: More than 90 percent complete• Next steps: Submit operating license application by year end; Load nuclear fuel next June; power generation by the end of 2015• Investment: Since work was restarted five years ago on the half-finished Unit 2, TVA expects to spend another $4.2 billion to $4.5 billion to complete the reactor.Source: Tennessee Valley Authority

More than four decades after construction began at the Watts Bar Nuclear Plant, nearly 3,200 TVA and contract employees are working around the clock to finish what should be America’s first new nuclear reactor of the 21st century.

Despite previous delays and cost overruns, the head of the final $4 billion-plus construction phase for the Unit 2 reactor at Watts Bar said Tuesday the project “is on time and on budget” and should be completed next year.

“We are still moving ahead toward being able to generate power by December 2015,” TVA Senior Vice President Mike Skaggs said.

But before nuclear fuel is loaded in a second reactor at Watts Bar, the Tennessee Valley Authority must still gain regulatory approval for an operating license for the Unit 2 reactor.