VW projects moving toward finale

The Industrial Board for the city met Tuesday to discuss construction at the Enterprise South industrial park, including updates on several projects to benefit Volkswagen.

Steve Leach, administrator of public works for the city, said the overall project is on track and on budget, and offered insight into the few remaining projects in which the city still has a hand.

The pedestrian bridge connecting Volkswagen’s training center to the assembly plant is well under way, with the majority of the bridge’s spans having been constructed in Colorado, Leach said.

Workers would begin pouring the piers to support the bridge’s 80-foot height next week, he said.

Meanwhile, Volkswagen’s finishing building, where customer requested modifications are made to vehicles before they are shipped, is about 60 percent complete, Leach said.