How do you sell a nuclear power plant? TVA may soon find out

tvboard-vote-sale-bellefonte-nuclear-plant
tvboard-vote-sale-bellefonte-nuclear-plant

Bellefonte Nuclear Power Plant

› Location: 1,600 acres between Highway 72 and the Tennessee River in Hollywood, Ala. › Investment: More than $5 billion, excluding most interest and maintenance expenses incurred over the past decade and a half. › Remaining debt: Most of the investment has already been written off, but $1.3 billion remains on the TVA books › What is on the site: Two unfinished Babcock and Wilcox pressurized water reactors, plus two cooling towers, switch yard, transmission lines and training facility and offices › History: Construction began in 1974, was suspended in 1988 on original units. In 1997, TVA considered using some of the infrastructure to construct a natural gas power plant but later abandoned those plans. Planning began to put a new generation of Westinghouse units on the site in 2006, but that was canceled in February, 2016. › What’s next: TVA board will consider a proposal Thursday to declare the property surplus and pursue its sale

Nearly 43 years after construction began, the Tennessee Valley Authority may pull the plug on the Bellefonte Nuclear Power Plant this week and look for a buyer for the 1,600 acres that house the unfinished reactor buildings, cooling towers, administrative offices and switchyards in Hollywood, Ala.

TVA directors on Thursday are scheduled to consider the future of Bellefonte, where TVA has invested more than $5 billion to build and maintain the mothballed power plant over the past four decades.

TVA’s vice president of stakeholder relations, Joe Hoagland, said Monday that TVA determined it would be too expensive to try to finish Bellefonte and it won’t need the power for at least the next two decades.

“When Bellefonte was evaluated as part of our integrated resource plan, it was not picked as a viable alternative for the next 20 years so we are trying to consider the best options for that site,” he told the TVA Regional Energy Resource Council Monday.