EL PASO, Texas (AP) – Nearly 5 miles of rail have been laid, and the overhead cable system is nearly done.
The El Paso Times reports it’s been about 15 months since work on the $97 million El Paso streetcar project began, and it is now about 95 percent complete.
The maintenance facility stands ready to receive the vintage cars that are getting scraped, buffed and painted – and receiving a technological boost – before they start making their way back to El Paso this spring.
Much work continues behind the scenes, but by the end of the year the streetcars will once again carry passengers along the streets of Downtown and West Central El Paso.
For now, expert streetcar restorers at Brookville Equipment Corp. in Pennsylvania continue to refurbish six of the original vintage President’s Conference Committee streetcars that rolled along El Paso streets until 1974 and then sat rusting in the open desert on El Paso International Airport property for 40 years.