Skip to main content
Monday, November 16, 2026Nov 16

Meigs County landowners claim TVA too vague, broad in condemnation action to take their land

Workers uncoil line at the base of a new TVA transmission tower in 2011.
Workers uncoil line at the base of a new TVA transmission tower in 2011.

Landowners in Meigs County contend TVA has been too vague about its plans for a new transmission line and too willing to tear up virgin forests to power its new system control center near Georgetown.

In a legal motion filed against TVA’s attempt to gain access to their property, Meigs County landowners Greg Vital, John and Bridget Vantiegham and Cornerstone Farm have asked U.S. District Court Judge Sandy Mattice to reconsider his order to allow TVA temporary access on to their private property to determine where a new high-voltage transmission line needed might be sited to supply a $300 million power control center it plans to open in south Meigs County by 2023.

“TVA has given Mr. Vital four possible routes it could use to run power lines over his property,” Chattanooga attorney Crews Townsend wrote in an 8-page motion challenging the way TVA is using its eminent domain rights. “Three of these run straight through virgin forest, which Mr. Vital uses for hiking, horseback riding, and other purposes. One option also runs through a field on which he grows crops and uses as a dove field during season. Mr. Vital has no idea what his present rights are or what the TVA will do to his property before a formal condemnation proceeding is filed.”

TVA said it wants access to the properties to conduct surveys, ground tests and other engineering work needed to build towers and a 161,000-volt transmission line for about 4.25 miles on a 100-foot wide right-of-way where the new line would be built to carry power to the new system operations center and its 200-employee staff.

TVA bought 167 acres near Georgetown in the summer of 2017, but it only revealed its plans in August of 2018 for a new system operations center to replace the current site downtown in the TVA Chattanooga Office Complex. Most of the center’s 240 employees will move to the new remote site near Gunstocker Creek off Highway 58 along Highway 60 once the facility is built and running by 2023.