State monitor warns on Ga. nuclear plant costs

In this photo taken Friday, June 13, 2104, two men work a new reactor construction is shown at Plant Vogtle nuclear power plant in Waynesboro, Ga. A recent assessment from a state monitor said publicly that it was not prudent for the electric monopoly to be spending on a multi-million construction effort without having a locked-down construction schedule.   (AP Photo/John Bazemore)
In this photo taken Friday, June 13, 2104, two men work a new reactor construction is shown at Plant Vogtle nuclear power plant in Waynesboro, Ga. A recent assessment from a state monitor said publicly that it was not prudent for the electric monopoly to be spending on a multi-million construction effort without having a locked-down construction schedule. (AP Photo/John Bazemore)

ATLANTA (AP) – Public watchdogs are giving Southern Co. a between-the-lines warning that building a multibillion-dollar nuclear plant in Georgia without a detailed construction schedule could trigger financial penalties.

That warning came in a report filed by a nuclear engineer and an analyst who work for state regulators and monitor the construction of two new reactors at Plant Vogtle in eastern Georgia.

The Public Service Commission has warned for at least two years that Southern Co. subsidiary Georgia Power is relying on an outdated project schedule that contains almost no detail after December 2015, even though construction will continue for several more years.

Nuclear engineer William Jacobs Jr. and financial analyst Steven Roetger said building a complex, first-of-its-kind project without a schedule was unreasonable.

“In fact it runs counter to any prudent project management, nuclear or otherwise,” goes against the project’s construction agreement and an industry group’s own recommendations for construction, Jacobs and Roetger wrote in a semi-annual report.