Two bridges over Interstate 24 in Chattanooga will remain closed until early 2025 after a setback, but the rest of the Interstate 75-Interstate 24 interchange reconstruction project remains on track for completion by late next year.
Work to replace substandard bridge beams at South Moore and McBrien roads was completed this week. The bridges were originally to be reopened this month.
“The project is approximately 40% completed,” Beth Emmons, spokesperson for the Tennessee Department of Transportation, said in an email. “The beam replacement and delays incurred with it did not affect the overall completion date.”
The project price tag remains unchanged at $161 million, Emmons said. Charleston, Tennessee-based Wright Brothers Construction Co. was the low bidder. Wright Brothers did not respond to a recent request for comment on the beam replacement.
In May, Joelle M. Cavitt, Wright Brothers’ director of marketing, said the shortcomings were found in January and reported to state officials. Cavitt said once the beams were replaced, construction of the bridges’ concrete decks could resume. The company must bear the cost of the replacement.